Arizona Department of Transportation SR 179 Improvement Project
800.529.2876 www.scenic179.com pr@scenic179.com
Welcome to the State Route (SR) 179 Project Weekly Construction Update - your electronic connection to the SR 179 Project with the most current information on construction plans and activities.
What to Watch for Week of July 20, 2009
Oak Creek Bridge Update
Crews are examining how to remove an underground section of the old bridge abutment near Tlaquepaque in the most cost effective and environmentally sensitive way. There will be no visible work on the new bridge above ground while this work is being done. The bridge is still on schedule to be completed by the end of 2009 or early 2010.
Traffic Shift between Bowstring Drive and Morgan Road
Traffic will be shifted to the east between Bowstring Drive and Morgan Road on SR 179. Please drive carefully and follow all traffic control devices. Bowstring Drive is now open.
Pedestrian Bridge Open at Oak Creek
The pedestrian bridge is complete. A temporary access to the pedestrian bridge remains open to the public. Please note that this access may be restricted due to final sidewalk, wall and roadway bridge construction at various times through the remainder of the year.
Landscaping Activities Through Business District
The landscape contractor, Recon, has begun landscape activities from the Y intersection to south of Ranger Road and near the Inn at Oak Creek to Canyon Drive. Please note the first work will involve placement of the irrigation system and removal of weeds. Actual plant and rock mulch placement will occur in a few months.
Please note: Changes to construction plans can happen frequently due to weather, equipment and personnel availability. We try to anticipate construction activities a week in advance but changes may occur. Intermittent lane closures, with short delays, may not always be known in advance.
For a complete listing of freeway and highway restrictions across Arizona visit ADOT's Travel Information Site at www.az511.com or call 5-1-1.
If you have information for the Scenic 179 construction updates, please send it to pr@scenic179.com or fax to 928.204.9835. To change your e-mail address, add someone new, or request a text version of this update, please e-mail pr@scenic179.com. |