Arizona Department of Transportation SR 179 Improvement Project
(800) 529-2876 www.scenic179.com pr@scenic179.com
Welcome to the State Route (SR) 179 Project Weekly Construction Update - your electronic connection to the SR 179 Project with the most current information on construction plans and activities.
Special Update for Week of July 7: Construction Begins at Y Intersection
Crews worked diligently last week to prepare the Brewer Roundabout, which will assist traffic movement during the Y reconstruction.

To see how to navigate the area using the new roundabout, download a printable PDF diagram here (pdf version).
This week, one of the most complex parts of the SR 179 Improvement Project will be underway: the reconstruction of the Y Intersection. Below is a photo simulation of what the completed intersection will look like.
ADOT's construction team has developed a plan for this difficult task to be completed in as little time as possible. Crews will work around the clock, seven days a week to completely rebuild the intersection before the busy fall tourism season.
Construction at the "Y" will be divided into two phases, building the new roundabout intersection one half at a time. During Phase 1 (July), crews will build the half of the roundabout closest to the Hyatt and phase 2 (August), will be the other half of the roundabout.
Click here to view a diagram that depicts traffic movements during Phase 1. ADOT is conducting an intensive communications campaign to inform the community and visitors about the construction and related traffic patterns. Our PowerPoint presentation about the task is now available to view. Call 602-750-7139 to schedule a meeting or presentation with your organization about the work.
Business access is open during construction. Please take the time to plan ahead for your travels through the construction zone, and be sure to visit your local businesses during this time.
Please note: Changes to construction plans can happen frequently due to weather, equipment availability and personnel issues. We try to anticipate construction activities a week in advance but changes may occur. Intermittent lane closures, with short delays, may not always be known in advance.
For a complete listing of freeway and highway restrictions across Arizona visit ADOT's Travel Information Site at www.az511.com or call 5-1-1.
If you have information for the Scenic 179 construction updates, please send it to pr@scenic179.com or fax to 928-204-9835. To change your e-mail address, add someone new, or request a text version of this update, please e-mail pr@scenic179.com. |